Overall funding for the Telerobotics Program is established in the annual submission of the NASA budget request to Congress. Input to this funding decision process is gathered from potential users and developers during the development of the annual OSAT technology plan. This plan is an integral part of the annual OACT budget development cycle, and includes input from the NASA field centers and the NASA Headquarters user codes. The planning cycle is illustrated in Figure 3-5.
Breakout of the overall funding level to the individual task elements of the program is determined by the Telerobotics Program Manager. Input to this funding decision process is gathered at the annual spring meeting of the TRIWG, at which program participants present task proposals for the following fiscal year. Following a funding determination by the Telerobotics Program Manager, the planned budget for the next fiscal year is released to the TRIWG and incorporated into the Telerobotics Program Plan. That budget, and that document, is used as the basis for the preparation of annual RTOP documents which detail planned task activities, objectives, schedules, and participants.
When the current tasks being worked in the various elements of the work breakdown structure are completed it is anticipated they will be replaced with other tasks within the same element. The TRIWG will continue to monitor the needs and results in each of the technology elements, and rebalance as appropriate.

Figure 3-5 OSAT Budget Cycle
The Telerobotics Program funding summary by program elements from FY95 through FY99 is shown in the following table. The funds for FY95 are actual expenditures, and those shown for FY96 through FY99 are planned funding levels. The funding is shown by task in the program and organizational element within the Spacecraft Systems Division budget structure (with corresponding Unique Project Numbers, or "UPN"s).
| Telerobotics Program Plan Budget - October 1, 1995 | |||||||
| UPN | Task Title | Center | FY 95 (*) Actual | FY 96 Plan | FY 97 Plan | FY 98 Plan | FY 99 Plan |
| 233-40-41 Manipulation | |||||||
| 1 | Micro Lander Manipulation | JPL | $600 | $600 | $600 | $650 | |
| 2 | Calibrated Synthetic Viewing | JPL | $275 | $400 | | ||
| 3 | SSF Telerobotic Maintenance | JSC | $400 | $500 | | ||
| 4 | ISSA Repair & Maintenance | JSC | $1000 | $1000 | $1500 | ||
| 5 | RSI Technology Transfer | JPL | $400 | $240 | | ||
| 6 | Ranger Visual Inspection | JPL | $200 | $300 | | ||
| 7 | Free Flying Camers for EVA | UMd/JSC | $400 | $550 | $750 | $1000 | |
| 8 | Rander Dexterous Arm Control | JPL | $350 | $300 | $300 | | |
| 9 | VR for Free Flying Robots | ARC | $200 | $135 | $300 | $300 | $300 |
| 10 | Light, Compact Muscle Actuators | JPL | $214 | $175 | $180 | | |
| 11 | Multiple Autonomous Systems | ARC/Stanf | $600 | $500 | $500 | $500 | $500 |
| 12 | PARIS | ARC | $250 | $300 | $300 | $300 | |
| 13 | Redundant Robotic Systems | JSC/UT-A | $300 | $300 | $300 | $250 | $250 |
| 14 | Program Management | JPL | $180 | $165 | $150 | $150 | $150 |
| 15 | Program Reserve | HQ | $60 | $500 | $500 | $500 | |
| Subtotal | $3030 | $4139 | $5375 | $4580 | $4500 | ||
| 233-40-42 Mobility | |||||||
| 1 | VR At Planetary Distances | JPL/ARC | $400 | $400 | $400 | $400 | |
| 2 | Exploration of Small Bodies | JPL | $870 | $1000 | $1000 | $750 | $750 |
| 3 | Planetary Aerobot Mobility | JPL | $500 | $500 | $500 | | |
| 4 | Rover Technology (**) | JPL/MIT | $2150 | $1800 | $1800 | $1500 | $1500 |
| 5 | VR for Rover Control | CMU | $250 | $250 | | ||
| 6 | Lunar Telescope Assembly | CMU | $225 | $225 | $450 | $450 | |
| 7 | Lunar Rover Technology | CMU | $380 | $500 | $500 | $500 | $750 |
| 8 | Nano-rover Technology | JPL | $450 | $550 | $600 | $700 | |
| 9 | Passive Proximity Sensing | CMU | $250 | $250 | | ||
| Subtotal | $3400 | $5375 | $5475 | $4700 | $4550 | ||
| 233-40-43 Integrated Systems | |||||||
| 1 | Space Operations | UMd | $400 | $450 | $500 | $500 | $500 |
| 2 | Robotics Engineering Consortium | CMU | $1000 | $500 | $1000 | $1000 | $500 |
| 3 | Micro Telerobotics (RAMS) | JPL | $600 | $500 | $800 | | |
| 4 | Robot Control Architecture | CMU | $100 | $150 | | ||
| 5 | Remote Scientist (***) | JPL | $1050 | $1200 | $1400 | $1500 | |
| 6 | Lunar Rover Demonstration | CMU | $870 | $750 | $750 | $750 | $500 |
| 7 | HAZBOT Completion | JPL | $100 | | |||
| 8 | Robotics Commercialization | JPL | $1000 | $1000 | $1500 | ||
| Subtotal | $2870 | $3450 | $5400 | $4650 | $4500 | ||
| 233-40-44 Flight Experiments | |||||||
| 1 | Ranger Flight Experiment | UMd | $1800 | $1925 | $1000 | $600 | |
| 2 | Ranger Launch Cost Deposit | Hq | $800 | $2000 | $8000 | | |
| 3 | Mesur Pathfinder | JPL | $8600 | $5800 | $2000 | | |
| 4 | External Work System | JSC | $3500 | $3500 | $3000 | $3000 | |
| Subtotal | $10400 | $12025 | $8500 | $11600 | $3000 | ||
| Total | $19700 | $24989 | $24750 | $25530 | $16550 | ||
| (*) Does not include ALL FY 95 tasks - only those continued into FY 1996. For a complete list of the FY 1995 program activities, refer to the FY 1995 Telerobotics Program Plan (**) includes MIT/Brooks - $250K and MIT/Dubowsky - $200K (***) includes MIT/ Salsbury - $250K | |||||||
Figure 3-6 Planned Program Budget (Dollars In Thousands)